Quarter ended financial report December 31, 2020
For the quarter ended December 31, 2020
1. Introduction
This quarterly report has been prepared by management as required by section 65.1 of the Financial Administration Act and in the form and manner prescribed by the Treasury Board GC 4400 Accounting Standard. It should be read in conjunction with the Main Estimates. This report has not been subject to an external audit or review.
1.1 Authority and Mandate
As outlined in the Invest in Canada Act, for the purpose of supporting economic prosperity and stimulating innovation in Canada, IIC’s mandate is to:
- promote foreign direct investment in Canada and attract and facilitate that investment; and
- coordinate the efforts of the government, the private sector and other stakeholders with respect to foreign direct investment in Canada.
1.2 Basis of Presentation
This quarterly report has been prepared using an expenditure basis of accounting. The accompanying Statement of Authorities includes IiC’s spending authorities granted by Parliament and those used by the IiC, consistent with the Main Estimates, Supplementary Estimates and Treasury Board vote transfers for the 2020-21 fiscal year. This quarterly report has been prepared using a special purpose financial reporting framework designed to meet financial information needs with respect to the use of spending authorities.
The authority of Parliament is required before money can be spent by the government. Approvals are given in the form of annually approved limits through appropriation acts, or through legislation in the form of statutory spending authority for specific purposes.
When Parliament is dissolved for the purposes of a general election, section 30 of the Financial Administration Act authorizes the Governor General, under certain conditions, to issue a special warrant authorizing the Government to withdraw funds from the Consolidated Revenue Fund. A special warrant is deemed to be an appropriation for the fiscal year in which it is issued.
IiC uses the full accrual method of accounting to prepare and present its annual financial statements that are part of the departmental results reporting process. However, the spending authorities voted by Parliament remain on an expenditure basis.
2. Highlights of the Fiscal Quarter and Fiscal Year-to-Date (YTD) Results
2.1 Statement of Authorities
As reflected in the attached Statement of Authorities, IiC’s total authorities has slightly decreased to $34.2 million (5%) in 20-21, down from the previous year of $36 million.
2.2 Statement of Department Budgetary Expenditures by Standard Object
As per the attached Budgetary Expenditures by Standard Object, total year-to-date net budgetary expenditures (April to December) represent 42% percent of total budgetary authorities available for use.
As shown in the below statements, IiC third quarter expenditures are $3.2 million lower than the year before. This variance is largely due to cancellations in key international in-person events and the inability to travel in 2020-21 due to COVID-19. To mitigate this variance IiC has actively re-allocated its budget to an integrated advertising campaign and expects a large portion of those expenditures to occur in Q4 of 2020-21.
3. Risks and Uncertainties
Operational risks
There is a risk that Covid-19 will limit IiC’s ability to achieve many aspects of its mandate. To minimize this risk, IiC has continued actively engaging with investors and partners to better understand the COVID-19 impact on expansion plans and their business more broadly. IiC has also strengthened its research activities to better understand the impact of the pandemic on investments and to provide information and data to partners and clients. In-person events and international conferences have been cancelled or postponed; however, where possible, IIC remains active and engaged through online event participation.
4. Significant Changes in Relation to Operations, Personnel and Programs
No significant changes to report.
Approved by:
Original Signed by
Ian Mckay
Chief Executive Officer
Original Signed by
Katie Curran
Chief Administrative Officer
Ottawa, Ontario
January 29, 2021
Invest in Canada
Quarterly Financial Report
For the quarter ended December 31,2020
Statement of Authorities (unaudited)
(in thousands of dollars) | Fiscal Year 2020-21 (in thousands of dollars) | Fiscal Year 2019-20 (in thousands of dollars) | ||||
---|---|---|---|---|---|---|
Total available for use for the year ending March 31, 2021* | Used during the quarter ended December 31, 2020 | Year to date used at quarter-end | Total available for use for the year ending March 31, 2020* | Used during the quarter ended December 31, 2019 | Year to date used at quarter-end | |
Bugetary Authorities Vote 1 - Program Expenditures |
34,292 | 4,551 | 14,384 | 36,057 | 7,708 | 15,209 |
Less: Revenues netted against expenditures | ||||||
Total Bugetary Authorities | 34,292 | 4,551 | 14,384 | 36,057 | 7,708 | 15,209 |
*Includes only Authorities available for sue and granted by Parliament at quarter-end.
Invest in Canada is responsible for all employee benefit and pension contributions
Invest in Canada
Quarterly Financial Report
For the quarter ended December 31, 2020
Budgetary expenditures by Standard Object (unaudited)
(in thousands of dollars) | Fiscal Year 2020-21 (in thousands of dollars) | Fiscal Year 2019-20 (in thousands of dollars) | ||||
---|---|---|---|---|---|---|
Planned expenditures for the year ending March 31, 2021 | Expended during the quarter ended December 31, 2020 | Year to date used at quarter-end | Planned expenditures for the year ending March 31, 2020 | Expended during the quarter ended December 31, 2019 | Year to date used at quarter-end | |
Expenditures: Personnel |
8,642 | 1,712 | 5,689 | 7,506 | 1,560 | 4,484 |
Transportation and Communications | 1,768 | 12 | 38 | 1,905 | 481 | 978 |
Information | 10,475 | 1,297 | 2,754 | 7,844 | 805 | 1,813 |
Professional and Special Services | 12,532 | 1,631 | 5,578 | 16,234 | 4,429 | 6,389 |
Rentals | 160 | 119 | 184 | 300 | 18 | 479 |
Repair and Maintenance | 200 | 0 | 4 | 120 | 8 | 11 |
Utilities, Material and Supplies | 50 | 9 | 15 | 1,025 | 25 | 109 |
Acquisition of land, buildings and works | 85 | - | - | - | 256 | 631 |
Acquisitions of Machinery and Equipment | 380 | 26 | 139 | 1,033 | 124 | 308 |
Other Payments | - | 18 | 17 | - | 2 | 6 |
Total Gross Budgetary Expenditures | 34,292 | 4,551 | 14,384 | 36,057 | 7,708 | 15,209 |
Total Net Budgetary Expenditures | 34,292 | 4,551 | 14,384 | 36,057 | 7,708 | 15,209 |